As part of the Archerfield Airport Corporation’s industrial development master plan, 24 hectares of land on the north-western boundary of the airport is being developed for industrial sub-division by Hansen-Yuncken.

PSM was engaged to prepare a bulk earthwork economic construction specification including roles and responsibilities. The specification allowed for a broad range of materials to be incorporated and maximum use of the industrial warehouses, and associated pavements and driveways. PSM also undertook a continuous audit of the earthworks.

OPPORTUNITIES

Providing a cost-effective solution by keeping and using the site’s own material was a key focus of the project.

Engineering and technical opportunities included:

  • Difficult site conditions with high-plasticity clay
  • Cost implications of removal of the clay layer and replacing with imported fill.

APPROACH AND INNOVATION

Following rigorous assessment and modelling, PSM’s tailored approach included:

  • Targeted investigation of site involving test pits and laboratory testing to identify problematic site conditions
  • Provision of site-specific earthworks specification and geotechnical advice focusing on use of material from the site
  • Incorporation into the earthworks of marginal material from the cut areas
  • Follow-up with client and earthworks contractor on implementation of the earthworks specification
  • Audit and certification of completed earthworks.

OUTCOMES

PSM’s engineering specifications, backed up by regular site visits, inspections and approvals prevented the need to remove and dispose of large quantities of material resulting in significant cost savings to the client. The specification allowed for a broad range of materials to be incorporated and maximum use of the industrial warehouses, and associated pavements and driveways. 

The PSM earthworks audit led to increased confidence that the earthworks complied with specifications and achieved the required performance.

Services: #Geotechnical #plasticity clay

get in touch

Contact Us

For expert advice, reach out to our team today.

    SUBSCRIBE TO STAY IN TOUCH

    Receive the latest news and updates straight to your inbox.
    footer certificationfooter certificationfooter certification
    Technically Assured Organisation
    Locations

    Sydney

    G3, 56 Delhi Road
    North Ryde NSW 2113

    BRISBANE

    Level 6, 500 Queen St
    Brisbane Qld 4000

    PERTH

    Level 3, 22 Delhi St
    West Perth WA 6005

    MELBOURNE

    Shop 4, Suite 4, 23-31 Gheringhap Street
    Geelong VIC 3220
    Contact us
    Locations

    Sydney

    G3, 56 Delhi Road
    North Ryde NSW 2113

    BRISBANE

    Level 6, 500 Queen St
    Brisbane Qld 4000

    PERTH

    Level 3, 22 Delhi St
    West Perth WA 6005

    MELBOURNE

    Shop 4, Suite 4, 23-31 Gheringhap Street
    Geelong VIC 3220
    Contact us
    Footer Certification
    Footer AEC logo
    © Pells Sullivan Meynink